A transformer can have spare total capacity while one phase is already constrained.
Explore one illustrative evening peak: 48 homes, hot water and three EV chargers supplied by a 200 kVA transformer. Customer phase connections are initially unknown to the network operator. Move a home to another phase or manage its load to see how currents and voltages change at this same point in time.
–
Phase data helps in two ways. It lets the EDB fix the imbalance that is already there by reassigning existing customer connections without replacing the transformer or feeder. And it lets new load be connected, or load be managed, where it counts. Reducing demand on another phase may provide much less relief at the constrained location. Phase and neutral coupling mean that the voltage effect also depends on where loads are connected.
Try System-level and observe which phases respond. Each press selects available loads at random, so the outcome varies. Reset, then try LV-level, phase-aware to target the phase carrying the highest current. Compare the actual kW removed as well as the current and voltage relief: whole EVs and cylinders give discrete steps. Balance phases reassigns whole customer connections at this snapshot; a real phase-swap plan needs time-series checks before implementation.
Keys: B balance · F LV-level, phase-aware managed load · G system-level managed load · E new EV · R reset
Illustrative values are conditional on the peak being a binding planning constraint and the intervention providing dependable relief. Each option is valued the same way: how long it delays the same reinforcement of this transformer, and what that delay is worth using an illustrative discount rate. The calculation projects this peak-load case to an assumed phase-current planning limit. Crossing that limit in a single snapshot does not by itself establish that reinforcement is due: duration, thermal history, voltage, reliability and operating options need assessment. A single growth rate describes LV load poorly, so every result is shown at 1%, 3% and 5% a year.
| Option | Phases (kVA) | Effective peak | Time to assumed limit | Deferral value vs as shown | ||||
|---|---|---|---|---|---|---|---|---|
| 1% | 3% | 5% | 1% | 3% | 5% | |||
Deferral value only exists where a transformer is heading for its limit. This scenario extrapolation takes Vector’s share of 200 kVA units (2,630 of 22,358 records) and the share of those above 80% utilisation (about 14%), applies them to New Zealand’s 196,885 distribution transformers, and values each transformer by how close it is to its rating.
This extrapolation is not a measured national opportunity and does not follow the interactive street, so it uses a fixed reference case rather than the lab: transformers above 80% are spread evenly between 80% and 100% utilisation, and an assumed half carry a 40:30:30 imbalance, close to the street’s starting split of –. The rest are treated as balanced and benefit from managed load only.
| Step | Value |
|---|
| Utilisation | Due with 40:30:30 | Value each |
|---|
Rating and utilisation counts are supplied assumptions from a Vector GIS summary (22,358 records); the extract and utilisation definition have not been independently verified for this page. Applying this mix nationally assumes it is representative; the 50% imbalance share and uniform utilisation bands are scenario assumptions. RAB and capex from the Commerce Commission, Total electricity distribution — year to 31 March 2025 [1]. Values are net of phase-swap costs, before paying for managed load.
A transformer’s nameplate is shared across three phases, but customers are connected one phase at a time. These indicators use different bases: the first two describe transformer-wide kVA; the third describes kVA on one limiting phase. They are not interchangeable measures of connection capacity. This page values deferral on the fullest-phase count, a balanced-equivalent index of the highest phase current, rather than a full thermal or hosting-capacity assessment.
Rating minus total customer load, across all three phases. Excludes network losses and ignores the distribution of load between phases.
Rating minus total load minus the neutral component, a simplified comparison inspired by the Dewesoft analysis, not a transformer thermal model. Imbalance costs capacity roughly in proportion to the neutral current.
Current margin on the heaviest phase, expressed as per-phase kVA at the nameplate voltage. The assumed 200 kVA / 415 V rating gives 278 A per phase. Multiplying this margin by three gives the balanced-equivalent index used in the valuation; it is not guaranteed usable connection capacity.
Dots on each conductor are drawn in proportion to the current in that span, so they thin out at every pole as customers take their share. Load flow: a four-wire unbalanced load flow runs in the page; independent validation is pending publication of the referenced OpenDSS test cases. 200 kVA transformer represented by a three-phase source and series impedance, 1.2% R and 3.8% X, 415 V line-to-line / 240 V line-to-neutral at no load (assumed source voltage), LV neutral earthed at the transformer. 400 m overhead line in ten 40 m spans, four 185 mm² aluminium conductors (0.164 Ω/km) on a flat crossarm at 8 m, with self and mutual impedances from Carson’s equations as computed by OpenDSS. MEN earth of 10 Ω at each pole. Constant-power loads at unity power factor, service lines ignored. The displayed voltage screening band is an assumed 207–253 V; it is not a site-specific compliance assessment. The neutral add-on method follows Dewesoft, Extending Grid Capacity.